UPDATE - FREEDOM BLVD. RECONSTRUCTION PROJECTThe anticipated completion date has been extended to April 2012. Remaining work includes completion of the Freedom Boulevard and Lincoln Street intersection and reconstruction of Freedom Boulevard between East High Street and Broadis Street. The City expresses appreciation to the Freedom Boulevard residents, businesses and travelers that pass through the construction area regularly. The project has been delayed for the following reasons: Additional improvements have been added to the project. Initially, the project included replacement of curb, gutter and sidewalk and reconstruction of the Freedom Boulevard from East high Street to Broadis Street. The City expanded the project scope to include more of Stanford Avenue and the intersection of Freedom Boulevard and Lincoln Street. The work at Lincoln Street will improve pedestrian safety and add landscaping. These additions have required more time. Unforeseen circumstances have increased the time to complete the project. These include poor soils in some locations that required removal, replacement and additional compaction. There have also been abandoned utilities that were not found until excavation took place and could not be addressed until the utility companies identified them and said that they could be removed. When the work extended into the holiday season, the City directed the contractor to reschedule work to minimize the impact on local businesses. Additional time was lost as the contractor had difficulty scheduling subcontractors. The most recent delay has come about because of a poor paving job at the Freedom Boulevard and Lincoln Street intersection. The City has required that the contractor remove the substandard paving and has asked the contractor to determine the cause of the paving problem and propose corrections before resuming work. WHAT'S NEXT?After the Freedom Boulevard Reconstruction project is completed, the City will begin discussions with the electric, telephone and television companies to remove the existing overhead wires and install them in the underground conduit and boxes that were installed recently. This is known as a "Rule 20A Project" and will take three to five years to plan and design. Not only are the utility poles and wires in the street removed, but the service connections from the street to the buildings are changed from overhead to underground. This will require coordination between the City and the individual property owners and tenants. If you have any questions regarding this project, please contact Murray Fontes at 831-768-3117. UPDATE - GREEN VALLEY RD. RETAINING WALL PROJECT Construction of the Green Valley Road Retaining Wall project is currently under way and should be complete by the end of March. The wall is on the west side of Green Valley Road between Main Street/Stake Route 152 and Melwood Way. One lane of traffic on south Green Valley Road at the project location will be closed at times to allow access by construction vehicles. After the wall is complete, it will be allowed to cure for a month and then a mural of slough scene will be painted on the face. For additional information on this project you can call Murray Fontes at 768-3117. CALTRANS-ROAD PROJECTS IN THE AREA CALTRANS-Salinas Road Interchange Project CALTRANS-Prunedale Improvement Projects CALTRANS-Highway 1 Soquel to Morrissey CALTRANS-Highway 1 & 17 Interchange Project CALTRANS-Road Information Update CRUZIO Traffic Information |
|
|
. TOILET REBATE PROGRAM Purchase and install a toilet rated to flush at a maximum of 1.28 gallons or less per flush and receive a rebate of up to $100. You must save your receipt and your old toilet. Rebates are not available for replacement of 1.6 gpf or 1.28 gpf toilets. Most toilets installed before 1992 are eligible for the rebate. Fill out the rebate application and submit to receive your rebate. Call Public Works & Utilities Customer Service at 768-3133 for more information. TOILET REPLACEMENT PROGRAM The City purchases the toilets (two styles) and contracts with Central Coast Energy Services to install them. Old toilets marked 1.6gpf are not eligible for free replacement. This program has no income restrictions. Call Energy Services at 1-888-728-3637 to see if your toilet(s) qualify. |
|
|
The FIRST layer of the resurfacing project of scheduled streets in Watsonville was completed. The project will resume in the Spring of 2012 and will be completed in Summer of 2012. You can view the entire schedule here. |
|
Read more...
|
|
|
|
<< Start < Prev 1 2 3 Next > End >>
|
| Results 1 - 4 of 9 |